RATBV aims to secure about 10 MW to charge buses at its new Brașov depot

At ROPAT 2026, the Technical Director of RATBV estimated that power at the Hărmanului Street depot will reach about 10 MW and spoke about the difficulty of obtaining permits.

Foto: ARSC / ROPAT 2026

RATBV and Brașov City Hall are working to increase the electrical power available at the depot on Hărmanului Street. Răzvan Crăciun, the operator's Technical Director, estimated that power will reach about 10 MW when the project is finished. The depot has been prepared both for the electric buses already in service and for the 88 the operator is expecting, he explained at the National Public Transport Congress on 19 November 2026 in Bucharest.

Răzvan Crăciun, Technical Director, RATBV S.A.
Răzvan Crăciun, Technical Director, RATBV S.A.

“The road has been hard, because of the permits,” Răzvan Crăciun said. Available charging power was, according to the Technical Director, one of the first difficulties RATBV met in moving to electric buses. He asked that operators be able to obtain permits faster once they have established and justified their power requirement.

Two grid connections for the Hărmanului depot

At 49 Hărmanului Street, the project provides for 157 parking spaces and one slow charger for each space. The power available from the grid determines how many buses can charge at the same time and at what power.

By summer 2026, RATBV had filed two requests with the county environmental authority to supply the depot from two substations. One of the planned connections starts in the commune of Hărman, the other in the Rulmentul area of Brașov, according to information published by Bună Ziua Brașov.

Work on the depot was completed in December 2025

European funding had been secured in May 2020, and construction began in November 2023. Besides the parking and charging areas, the complex includes a maintenance workshop, an area for periodic technical inspections and a bus wash.

Magda Peșu, CEO, Anadolu Automobil Rom
Magda Peșu, CEO, Anadolu Automobil Rom

Drawing on the experience of delivering electric vehicles, Magda Peșu, CEO of Anadolu Automobil Rom, explained in the same debate why grid works must be coordinated with the fleet purchase. When the buses arrive, the operator should already have both slow and fast chargers at its disposal.

Sources · Răzvan Crăciun at ROPAT · Magda Peșu on connecting chargers · The two planned power connections (in Romanian) · Works timetable and depot facilities (in Romanian)

23 November 2026 · transportpasageri.ro editorial team · Source: ROPAT